ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 1 B A 4 C A 3 D B 2 E C,D 5 F D 2 G F 2 H E,G 3 a. Draw the network. b. What is the critical path? c. How many weeks will it take to complete the project? d. Which activities have slack, […]